Duas unidades LIYI de 1500 kVA em contêiner fornecem agora energia contínua a uma mina de cobre no Haut-Katanga.

LIYI engineers recently completed commissioning of a 1.2 MW containerised power plant at a copper mining site in Haut-Katanga, DRC.

  • Two LY-1500C container units in automatic parallel operation
  • 20 ft ISO containers with sound attenuation and full weather protection
  • ComAp InteliGen synchronising control with remote monitoring
  • Commissioned in 9 days, including on-site training for local operators

"This project shows what matters most to African customers: fast delivery, fuel economy and service support that actually shows up," said the project manager. Spare parts for both units are stocked at a regional warehouse.